Growth and portfolio decisions
I weigh site economics and franchisee commitment when deciding which projects to advance or recover. At Sandhill, I recommended keeping the original site and renegotiated the terms that made it viable.
Target role: VP / Head of Development · Permanent, full-time
I help CEOs and founders decide where to expand, how much to invest, and which franchise projects to move forward. I’ve led development teams, owned departmental P&L and capital budgets, and set clear checkpoints from lease negotiations through opening day.
Scope matters: 45 is the career total across brands, 75 is the portfolio, and up to 35 projects ran concurrently at peak — not a single-brand snapshot.
01 — How I Lead
I weigh site economics and franchisee commitment when deciding which projects to advance or recover. At Sandhill, I recommended keeping the original site and renegotiated the terms that made it viable.
I owned departmental P&L and capital budgets. At Relentless Brands, I directed $12M–$15M+ in annual development and facilities capital and advised leadership on investment priorities and portfolio risk.
At Dogtopia’s Garden Home site, I negotiated approximately $489,000 in tenant improvement and landlord work allowances.
I led 4–7 direct reports and set checkpoints from letter of intent to closeout, including when tenant improvement allowances were claimed and when the claim package went to the landlord. That process helped me manage up to 35 concurrent projects.
I coordinated 16 ISI openings and secured Hyperice as an official sponsor of The Plunge House, adding a recovery offering and a revenue stream.
02 — Selected Development Work
When the franchisee wanted out midway through construction in Columbia, South Carolina, I recommended keeping the original site. I secured roughly $140,000 in additional tenant improvement allowances and about 12 months of rent abatement. The franchisee recommitted, the location opened, and a roughly $90,000 lease buyout was avoided. The project finished roughly $45,000 net ahead despite a mid-project contractor default.
As the sole point of direction for the design team, I helped bring an $878,000 preliminary construction estimate down to a $665,000 contract. I took over the build midstream, coordinated replacement vendors, and secured health department approval to meet the final opening date.
I moved millwork and other scopes out of the general contractor’s contract and bought them directly, reducing buildout costs from $127 to $106 per square foot.
Interlude — In Pictures
Photographed in the finished spaces — ISI Elite Training, Row House, Dogtopia, SweatHouz, and The Plunge House, delivered from LOI to opening day.

The training floor at ISI Cooper City — dual branded walls, kettlebell storage, and open floor ready for turf and rigs.

Glass-front entry and lobby at Cooper City — dark finishes and a clean sightline straight to the training floor.

The youth program gets its own glass-walled room inside Cooper City — branded entry doors and black granite wainscot.

Cooper City's turf run with the ISI mark set into the floor — sleds staged, medicine balls racked, and daylight across the training floor.

Full-height branded walls, turf, ropes, and racks laid out for class throughput — the ISI format, opened in Walnut Creek.

Dogtopia's Park playroom at Sun City — full-wall park mural, rubber flooring, and crate banks sized for daycare capacity.

The 9436 storefront in daylight — palms, fountain, and the orange Dogtopia sign over the arched entries.

The same entry at night, logo lit — glass front door glowing behind the palms and the ramped walk.

Houston's storefront under the orange pylon sign — matching awnings and daycare windows across the frontage.

Channel letters over full-height glass, geometric window film, and the front desk working from the sidewalk view in.

Cedar infrared sauna with the brand mark set above the bench — the heat half of the SweatHouz contrast circuit.

Frisco pairs a glass-front infrared sauna with a full-size cold plunge in a single private suite — marble-look tile throughout.

Frisco's marble shower — large-format marble tile, matte black rain head and controls, and penny tile underfoot.

The Frisco plunge on its own — black tub, black marble tile, and a backlit mirror setting the cold side of the circuit.

Iron Kidz gets a dedicated zone inside the facility — its own branded wall, scaled for youth training sessions.

Dimensional Plunge House signage on matte navy, brass peg detailing, and boucle seating — the first thing members see on entry.

Full cedar build — horizontal paneling, tiered benches, and the traditional bucket and ladle. Heat paired with the plunge hall next door.

Light wood lockers, rolled-towel shelving, LED-lit ceilings — and the brand manifesto set in dimensional letters on the wall.

The Wilmington storefront as the sign went up — ISI channel letters over the entry and the franchise message across the glass. The finished training floor, Iron Kidz room, and rig are in the cards that follow.

The full training floor at Wilmington — the city wall and turf lane on one side, the green hydrate pillar and dumbbell rack on the other.

Wilmington’s Iron Kidz room — the branded wall, a kids’ table and chairs, and the bright bean bag in the corner.

A bank of Concept2 SkiErgs set under the tall windows at Wilmington — conditioning capacity built into the floor plan.

The rig corner at Wilmington — wall-mounted pull-up bars over ISI-branded plyo boxes and slam balls, rubber wainscot throughout.

Panorama of the Row House studio as found — this space was remodeled and converted into an ISI Elite Training, delivered at $45K net cost.
See the conversion case study
The raised coach platform in the original Row House layout — stripped out and rebuilt as part of the $45K net-cost conversion to ISI.
See the conversion case study
The Row House studio under its blue class lighting — later remodeled into an ISI Elite Training for $45K net.
See the conversion case study
The Row House quote wall before the remodel — the brand shell that was turned into an ISI Elite Training at $45K net cost.
See the conversion case study
The studio from the coach’s view before conversion — same footprint, reborn as ISI Elite Training, with the full conversion delivered at $45K net cost.
See the conversion case study
The Raleigh studio after conversion — rower rows out, open training floor and the ISI turf lane in, photographed on site at $45K net cost.
See the conversion case study
The converted floor up close — the ISI logo inlaid in the turf lane, dumbbell rack staged, and the class screen mounted on the two-tone wall.
See the conversion case study
The converted studio from the street — brick frontage, the ISI Elite Training sign over full-height glass, and a full parking row out front in Midtown Raleigh.
See the conversion case study
The full Midtown Raleigh training floor in one view — Iron Sharpens Iron down the left wall, GRIT and the Raleigh city wall at the far end, turf lane in and rower rows gone.
See the conversion case study
Midtown Raleigh's floor ready for a session — dumbbells and cones set out under the Iron Sharpens Iron wall, bikes and ropes staged along the black wainscot.
See the conversion case study
Inside the Midtown Raleigh entry — the white ISI Elite Training desk under the Train for Life wall, member lockers banked to one side and retail to the other.
See the conversion case study
The white ISI front desk under the Train for Life wall — glass entry doors on one side, storefront glass pouring light in from the other, and the training floor straight ahead.

Another ISI reception — the branded desk against a black feature wall, with the training floor and Iron Sharpens wall opening up behind it.

From inside Cooper City looking out — the Iron Kids glass room on the left, the ISI Cooper City doors ahead, and the storefront beyond.

The Iron Kidz wall head-on — charcoal and lime lettering over black speckled flooring, with the room's screen mounted alongside.
An ISI storefront in wood and stone — the channel-letter sign, Now Hiring window graphics, and training imagery across the glass.

A Dogtopia storefront in dark metal panel and glass — a timber-lined entry canopy and the orange wordmark over the doors.
Dogtopia in painted white brick — orange channel letters, black railings, and the glass daycare entry at the corner.
Floor-to-ceiling daycare windows with dog decals, under the orange Dogtopia sign on corrugated metal siding.

A red-brick Dogtopia — lit signage, glass entry doors, and big daycare windows onto the sidewalk.
Inside a Dogtopia lobby — the orange brand wall, a mural-sized greeter by the door, and the curved front desk under the daycare screens.
Frisco's infrared sauna behind full-height glass doors — cedar benches glowing amber, with the plunge bench waiting outside.
The black SWTHZ front desk at Frisco — check-in under the framed coastal print, concrete floors, and the studio beyond.
A SWTHZ storefront in white stone tile — geometric glass film, a black-framed entry, and the sidewalk sign out front.
An infrared sauna under its color-therapy lighting — cedar benches, panel heaters on three sides, and the brand plaque on the back wall.
A full marble shower room — dual rain heads, matte black fixtures, grab bars, and penny tile underfoot.
SWTHZ in charcoal — white channel letters over geometric glass, set into a modern mixed-use frontage.
A contrast suite in black marble — the plunge in the foreground, the glass sauna behind it, and a backlit round mirror over the vanity.
SweatHouz's beauty bar — a lit vanity station with towels rolled and ready, set just off the studio floor.
The SWTHZ cold plunge in the foreground and the cedar sauna glowing at the end of the hall — the full contrast circuit in one view.

Down the Plunge House hallway — the dimensional logo on matte navy, woven pendants overhead, a leather bench along the wall, and the front desk at the end.
03 — The Proof
Not a claim — a board-reported result, with the contracts and pay apps behind it.
Cut by pulling scopes — including millwork — out of the GC contract and contracting directly with specialized vendors. Reported to the board March 20, 2023, as Director of Construction.
A full Row House studio remodeled and converted into an ISI Elite Training — a complete brand-to-brand conversion delivered at $45K net cost. Reuse of the existing footprint and disciplined scope control, instead of a ground-up buildout. See the conversion case study
Dogtopia — Huntsville, AL: $30K recovered in liquidated damages — the contract enforced as written when delivery slipped, with the damages collected back for the project.
$5,684,537 gross buildout across 8 new units in the Prospect Hill rollup, against $1,345,143 in TI received.
SweatHouz FF&E standardized at $100,805 / unit — the same discipline on every opening: competitive bids, tight change-order control (including reversing a PCO and voiding a duplicate CO), and landlord dollars captured before signing.
$134,294 TI collected — 100% of the tenant improvement allowance, ISI Elite Training HQ. The full landlord allowance for the headquarters buildout was drawn and received — collected to the last dollar, not left unclaimed at close-out.
04 — Project Record
Documented projects with the figure attached. Filter by brand.
| Project | Scope | Documented figure | Note |
|---|---|---|---|
| Dogtopia — Huntsville, ALLegacy Franchise Concepts | 7,954 SF · Ground-up / TI | $906,594 GC $940,640 total $30K LD recovered | Beam Team contract. Completed Mar 24, 2023 — $30K recovered in liquidated damages. |
| Dogtopia — Garden Home, ORLegacy Franchise Concepts | Full buildout | $1,420,801 contract $932,224 net | Net after TI & landlord allowances. |
| SweatHouz — Preston Royal, Dallas, TXLegacy Franchise Concepts | 3-bid process | $567,310 → $584,422 | After 3 PCCOs — change held to ~3%. |
| ISI — Tomball / Northpointe, TXRelentless Brands | Franchisee buildout | $335,766 contract | AIA Pay App #2: ~57% complete, Feb 29, 2024, 10% retainage. |
| Row House → ISI Elite TrainingRelentless Brands · Raleigh, NC | Remodel · Brand-to-brand conversion | $45K net cost | Former Row House studio in Raleigh, NC converted into an ISI Elite Training — full remodel delivered at $45K net. See the case study |
| ISI — Cooper City, FLRelentless Brands | Close-out | 12-item punch list | Formal punch list issued Dec 16, 2025 with franchise partner. |
| Relentless Brands HQISI / The Plunge House | Landlord TI draw | $67,147 drawn | 50% of $134,294 TI — invoiced Apr 30, 2024. |
Showing all projects.
05 — Negotiation
The negotiation is where the margin is made — before construction ever starts.
2,570 SF former F45 at $32.00/SF. If the landlord violates exclusivity: 50% rent, termination after 12 months, and reimbursement of unamortized TI + design fees. Plus 30 days' base rent abatement.
4,616 SF at $32.00 PSF with $28.00/SF TI. Negotiation cut the guarantee from 5 years to 3 and added 4 months at $0 rent + 120 days' abatement after rent commencement.
2,765 SF at $31.00/SF after five rounds of counters (Jan–Mar 2024). Late delivery costs the landlord 2 days' rent abated for every 1 day late.
~$140K TI + ~12 months free rent negotiated, then ~$75K in damages pursued after GC default — ~$45K net recovered for the project.
~$60K in contingency returned — budget discipline held through close-out instead of being spent because it was there.
City confirmed ISI classifies as a “commercial school” — permitted by right, parking at 1 per 222 SF, no planning approval needed. De-risked before the lease was signed.
Case Study — ISI Elite Training · Sandhill
Columbia, South Carolina. Lease strategy, landlord leverage, contractor documentation, and construction recovery protecting owner capital.
ISI Elite Training Sandhill was not a routine fitness build-out. The project became a complex development challenge involving lease exposure, landlord negotiations, contractor performance issues, disputed payment demands, and construction recovery. Halfway through the build — after the first 50% of the tenant improvement funding, roughly $110,000, had already been received — the franchise owner wanted out of the lease. He wasn't fully sold on the location and wanted a different site in a better complex instead. I stayed in his corner through the exit attempt — including advising him to form a second LLC to shield his assets in case the landlord pursued him for defaulting on the lease. The second property never got signed, so the owner came back to the original site and construction restarted.
Through direct conversations with the landlord, I identified the larger business driver: preserving signed leases to support the broader value and marketability of the shopping center. Once that was understood, the negotiation strategy changed. The project was repositioned around what the landlord actually needed — an active, committed tenant that supported the value of the development. That leverage produced the package that kept the owner in the deal: $140K+ in additional TI and roughly 12 months of rent abatement.
As contractor-related disputes escalated, the project record became one of the most important assets. Communications, field photos, scope status, payment history, punch items, and performance issues were organized to support the owner's position. The result was a more controlled outcome driven by evidence, not emotion. That record is why a replacement GC brought in on a roughly $75K scope — substantially late, with scope left incomplete — was paid nothing. It also exposed the original GC, Beam Team, which had claimed rough-in and final inspections had passed when they had not; the owner sued Beam Team as well.

The full training floor mid-build — ceiling grid and lights in, flooring going down over the concrete, materials staged along the walls.

Rubber flooring rolling out across the floor, boxes and scaffold staged — the floor taking shape bay by bay.

Across the floor toward the storefront glass — paint, trim, and punch work still under way.

Walls painted two-tone and the floor protected while the last finishes and fixtures went in.

A back room mid-build — black tile in on one wall, bare concrete on the other, lumber stacked for the next phase.

The same run from the other end — floor openings cut and the tile wall continuing down the length of the space.

A tiled bathroom mid-fit-out — fixtures set, trim and final protection still to come.

The bathroom program further along — mirror, grab bars, and the lit wall panel in place.

Water heater and electrical in the back-of-house utility room — the unglamorous rooms that make an opening possible.

The front desk still wrapped in plastic, scaffold up by the storefront glass — reception days from turnover.

The branded Sandhill storefront in the shopping center — the signed, performing lease the landlord needed to protect the center's value.

Sandhill's reception desk up close, finished — the same desk from the progress shots, with the branded face installed, the supplement display set, and the polished gray floor running into the studio.
The Sandhill project was stabilized through strategic negotiation, disciplined documentation, and hands-on construction leadership. This was not just a construction project. It was a capital preservation and project recovery assignment.
Case Study — Row House → ISI Elite Training · Raleigh, NC
Raleigh, North Carolina. An operating Row House rowing studio remodeled and converted into an ISI Elite Training — same footprint, new brand, delivered at $45K net cost.

The Row House studio as found — rower rows under the gold W, shot from the coach platform.

The same Raleigh studio after conversion — the rower fleet and coach platform out, an open training floor in, with the turf lane and the ISI mark set into it.

The Row House front desk as found — check-in tablets on the white counter, the entry opening behind it.

The front of house in the converted space — the white curved reception desk carried into the ISI layout, member lockers banked behind it, storefront glass at the entry.

The studio under Row House's blue class lighting — fixed rower rows facing the W wall graphics.

ISI's turf lane in place of the fixed rower rows — the ISI mark inlaid in the black turf, running the length of the converted studio.

“Further Together” — Row House branding across the back wall, over the rower fleet.

Where the quote wall stood — the ISI turf lane below and the large class screen mounted on the two-tone wall, the studio laid out for class throughput.

The illuminated Row House screen hanging over the studio, rower rows stretching out beneath it.

The full converted studio in one view — rubber training floor under the black ceiling grid, turf lane and screen wall at the far end, ready for opening.

The dumbbell rack staged on the turf lane, the ISI Elite Training lettering inlaid in the floor beneath it.

Across the rubber floor to the water fountains and the wall-mounted pull-up bar — two-tone walls under the black ceiling grid.

The pull-up rig and dual fountains on the gray wall — conditioning capacity built into the converted floor plan.

The studio from the turf lane — screen wall ahead, open floor beyond, final equipment still staging at close-out.

Dual fountains with a bottle filler set into the gray wall, speckled rubber wainscot running the height of the training zone.

The wide opening between front of house and the training floor — wood-look lobby flooring meeting the rubber studio floor.

Reception, lockers, and the retail wall in the converted front of house — the Row House water station still in place at turnover.

Thirty white member lockers carried through the conversion, stacked beside the desk — the old brand's podium by the door on its way out.

The storefront entry sequence was reused as found — full-height glass, the CAVA and the center visible across the walk.

White wave tile below, charcoal above — wall-hung sink, mirror, and grab bars in the refinished restroom.

The restroom off the locker wall — new signage on charcoal paint, dark plank tile running into the room.

The conversion worked out in marker on the existing floor plan — the turf zone and battle ropes drawn in over the Row House layout.

The brick Row House storefront, unit 130 — the frontage the conversion inherited.

The same brick frontage from the corner — full-height glass running down the entry side.

Inside the front door — the ROW HOUSE floor mat, member lockers, and the glass frontage as found.

The oversized W wall graphic under purple light, rowers lined up beneath it.

Row House kept a dumbbell rack and cubby storage by the window — the strength corner of the rowing studio.
The Raleigh conversion took a single-brand rowing studio and delivered a full ISI Elite Training inside the same walls for $45K net — the cheapest square footage is the space you already have, converted with discipline instead of rebuilt from scratch.
Case Study — The Plunge House · Charlotte, NC
The Platform, 3216 South Blvd Unit 202, Charlotte, NC 28209 (South End). The corporate flagship for a contrast-therapy concept — plunge room, saunas, and locker rooms on the second floor of a new mixed-use building, on a 10-year lease at $40/SF with landlord Investicore.
Cruz created the design intent package for the Plunge House concept. That package set the direction for the flagship build — the plunge room, saunas, and locker rooms — before he later became the person responsible for forcing the project across the finish line. His role on this project was design direction and, from mid-build onward, sole direction for the design team and the site.
Five GC bids leveled at $869K–$1,115K against an $878K preliminary budget. In January 2024, three value-engineering rounds cut the construction contract from the $878K preliminary estimate to a $665K lump sum — a 24.3% reduction on the construction contract. The GC fee was negotiated down from ~$80K to $65K. Net construction after TI: $463,540. The full $201,460 TI allowance was captured, with the 50% draw ($100,730) invoiced in April 2024. Increased vendor rebates by $5,000 per project across 16 projects ($80,000 total) by bringing on his own architect. Generated a 3% vendor rebate on lighting purchases, running ~$2,000 per quarter, and flat $1,000-per-project AV/IT vendor rebates across 16 projects ($16,000 total) by bringing on his own vendors.
Fire Marshal-driven fire-alarm additions were absorbed mid-stream. A twinned-furnace HVAC solution avoided a $10,000 change order. Owner-furnished tubs, saunas, and an ADA lift were procured directly — keeping critical contrast-therapy equipment on the owner's timeline rather than the GC's.
The prior project manager departed mid-build. From May 2024, Cruz was the design team's sole direction point. He walked the site May 19 and issued a 101-item punch list on June 4 with a five-day deadline and a documented $2,000/day delay cost. He issued a Notice of Termination for Cause on June 9, 2024, and personally locked the GC out of the site, finishing the build on site around the clock with new owner-direct vendors. When the GC refused scope, Cruz drafted owner-side liability releases so the work could proceed.
After repeated grand-opening postponements, Cruz personally drove the final opening date and made it — including personally securing the health department sign-off to open, required for the cold plunge operation. The club was staffed and operating into late 2025, with Cruz still managing its vendor and warranty items.
06 — Fractional
I take on select fractional engagements for emerging brands that need development leadership before they can support a full-time hire.
The pilot is structured as a monthly retainer for three months.
07 — Experience
Cruz Parmer is a development executive based in Charlotte, NC, and open to relocating nationally for a permanent VP / Head of Development role. His recent leadership experience includes Relentless Brands, supporting ISI Elite Training and The Plunge House, and Legacy Franchise Concepts, supporting SweatHouz and Dogtopia.
ISI Elite Training & The Plunge House. Site selection, LOIs and leases, design, construction, and openings across a national franchise pipeline.
SweatHouz and Dogtopia. Board reporting, cost-per-SF program, FF&E standards, multi-state buildouts and facilities.
12 years across architecture & planning and construction — including 2 years as an F&B construction PM — the base for the integrated real estate + construction approach.
Based in Charlotte, NC. Willing to relocate nationally for the right role.
08 — Testimonial
From clients who opened their first fitness business with Cruz guiding the lease, the build-out, and everything in between.
When we began the process of opening our fitness business, we quickly realized how complex commercial real estate, lease negotiations, and facility development could be. Having Cruz guide us through the process was invaluable.
From the very beginning, Cruz brought a level of knowledge, persistence, and professionalism that gave us confidence every step of the way. He played a critical role in negotiating our lease, helping us secure favorable terms while protecting our interests. His expertise also helped us identify opportunities to reduce costs during the build-out process, ultimately saving us money without compromising the quality of our business.
What stood out most was Cruz’s determination and commitment to helping us succeed. Whenever challenges arose, he remained engaged, solution-oriented, and relentless in pursuing the best possible outcome. His experience and understanding of the process helped us avoid costly mistakes and make informed decisions throughout the project.
Opening a business of this scale is no small undertaking, but Cruz’s guidance and advocacy helped make our vision a reality. We are incredibly grateful for his support and would highly recommend him to anyone looking for a trusted professional who truly goes above and beyond for his clients.
09 — Questions
What the role is, who Cruz Parmer is, and the record behind the full-time VP / Head of Development search.
Cruz Parmer is a development executive based in Charlotte, NC with 12+ years across franchise fitness, wellness, and multi-unit retail, available for VP / Head of Development roles. Most recently Director of Real Estate & Construction at Relentless Brands (ISI Elite Training, The Plunge House) and Executive Director of Construction & Facilities Maintenance at Legacy Franchise Concepts (SweatHouz, Dogtopia). Record: 45 openings, 75-unit portfolio, up to 35 concurrent projects, $12–15M+ annual capital.
A VP of Development owns growth end-to-end: site selection, LOI and lease negotiation, design, permitting, GC and vendor contracting, construction, and opening. Cruz runs a 10-phase system with a 280-day agreement-to-opening cycle — so real estate, construction, and openings never fall between departments.
Construction cost cut from $127 to $106 per SF. $134,294 TI collected in full for ISI HQ. ~$140K additional TI + ~12 months free rent at ISI Sandhills. A Row House → ISI conversion delivered at $45K net. $30K liquidated damages recovered at Dogtopia Huntsville.
For emerging brands that need development leadership before they can support a full-time hire, Cruz takes on select fractional engagements through a paid 90-day pilot — diagnose the pipeline, install the process, then run it and decide together about continuing. His primary search remains a permanent, full-time VP / Head of Development role. See Fractional Development Leadership.
10 — Contact
My primary search is a permanent, full-time VP / Head of Development role. Fastest is a call or email — based in Charlotte, open to relocating nationally.
Development executive based in Charlotte, NC, and open to relocating nationally for a permanent VP / Head of Development role. Recent leadership includes Relentless Brands — ISI Elite Training and The Plunge House — and Legacy Franchise Concepts — SweatHouz and Dogtopia.